In general, development of land requires a building permit and in many cases it also requires a planning permit and an environmental permit. The use of the completed building requires notification to the relevant authority or an occupancy permit.
If the site is not covered by a master plan, a planning permit must be obtained before submitting the application for the building permit. The law makes a distinction between planning permits for public developments and those for private schemes. “Private” planning permits are much more difficult to obtain. Obtaining a “private” planning permit requires a number of conditions to be fulfilled, including securing media connections (at least signing contracts with grid operators) and ensuring architectural compliance with neighbouring developments. The local authority architecture department has to prepare a “zoning analysis” in order to verify whether those conditions are met, and if not, whether they can be waived. The planning permit procedure may be suspended (at the city’s discretion) for up to nine months. If a master plan for a given development or territory is “obligatory”, the planning permit procedure is suspended until the adoption of the master plan.
The current form of the planning permit makes it possible for the authorities to approve only those developments which they in their discretion consider appropriate. Obtaining a planning permit may also turn out to be risky to the developer, as it has to satisfy the claims related to the restriction of use or loss of value of neighbouring plots caused by this decision. Planning permits may be obtained by any interested party, irrespective of whether such party holds a legal title to the site. They are also transferable into third parties. A planning permit specifies its validity period (usually two – three years). It expires if another entity obtains a building permit for the site, or if a master plan is adopted and the planning permit does not comply with the new plan (unless a final building permit has already been granted).
Building permits may be obtained if the project complies with the master plan and technical requirements. If there is no master plan then a building permit may be obtained if it complies with the planning permit and technical requirements. In this latter case, the building permit application must be submitted within the validity period of the planning permit. A building permit is usually composed of two basic elements: approval of the designs and permission to start the works. If the project is phased, the developer may request permission to start the works for the initial phase(s) only. In this case, the building authority must approve the “site development plan” (forming part of the building documentation) and detailed architectural designs for the initial phase. In order to obtain a building permit, the developer needs to hold a legal title to the site (not necessarily freehold – it may be even a simple lease).
The building permit documentation must be approved in advance by various authorities, including (as applicable): the sanitary inspector, environmental protection, cultural and heritage inspector, road management authority, work safety administration, fire marshal etc. A large part of the land in Poland is considered “agricultural” (the formal criterion is the relevant entry in the land register). In such a case, prior to issuing a building permit, the site should be excluded from agricultural use. This involves payments from the owner, in ten annual instalments, depending on the category of the land. In most cases, building permits are issued by the starosta (head of mid-level administrative unit called the powiat). In bigger cities, the functions of the starosta are exercised by the mayor. As with a planning permit, a building permit may be transferred to a third party, provided that it holds a title to the site and accepts conditions provided in these decisions.
An additional building permit issued by the monument restorer is required when it is proposed to do work to historically or architecturally important buildings.
Certain construction works do not require a building permit, but simply a notification to the building authority. The works may be started if the building authority does not raise any objections within 30 days from the notification. These works include among others: parking lots with no more than 10 spaces, certain temporary objects, fencing, certain advertising billboards, reconstruction and modernisation of roads, power and gas connections, irrespectively of whether such works are related to the construction of the building or work performed on an undeveloped land, except for works regarding structures entered into the register of historical monuments.
The provisions of the law on environmental information and environmental impact assessment expand considerably the scope of application of the “environmental decisions”. The law divides the investments between those which (i) may always significantly influence the environment and (ii) may potentially significantly influence the environment. For both an environmental decision will be required. Certain investments require preparation of an environmental impact assessment report due to their potential impact on the environment. The developments concerned include: most industrial facilities, parking lots or garages with usable area of 0.5 ha, shopping centres with usable area of more than 2 ha and many others. For others such requirement may be imposed by the authorities after an application for an “environmental decision” is submitted.
The developer has to obtain a “decision on environmental conditions” prior to obtaining a planning permit or filing for a building permit (and without the need to secure the title to the site). The decision on environmental conditions is valid for four years and will be binding on the building authority while granting the building permit. The four year term may be extended if the conditions specified in the decision on environmental conditions do not change and the project is developed in phases.
The use of the completed building or structure may be commenced upon notifying the relevant authority. The investor may take occupancy if the authority has not reported any objections within 21 days of the delivery of the notification. In some specified cases the notification is not sufficient and an occupancy permit is also required.
The use of building structures without notifying the relevant authorities or without the required occupancy permit is illegal. Apart from the administrative consequences of illegal use, such as a fine which may be imposed by the relevant authorities, the lack of notification or a occupancy permit causes fundamental problems concerning leasing or insuring the building.
Social Media cookies collect information about you sharing information from our website via social media tools, or analytics to understand your browsing between social media tools or our Social Media campaigns and our own websites. We do this to optimise the mix of channels to provide you with our content. Details concerning the tools in use are in our privacy policy.