Market activity

High. Romania’s BESS market is projected to double in size for a second consecutive year, reflecting the country’s rapid emergence as a European storage market. Romania has a developing and increasingly sophisticated corporate PPA market, supported by the liberalisation of directly negotiated bilateral contracts and a growing pipeline of merchant and partially merchant renewable projects. The market has seen growing interest in both physical and virtual PPAs, as well as more complex structures combining offtake, balancing, route-to-market and GoO arrangements. Developers, offtakers and lenders are increasingly combining PPAs with balancing, optimisation and storage solutions, including hybrid renewable-plus-storage structures. The market is also benefiting from the launch of CCP.RO, Romania’s first central counterparty for electricity contracts, which is expected to improve forward-market liquidity, reduce counterparty risk and facilitate longer-term hedging arrangements.

CMS (through joint teams in Romania and London) has worked on some of the first virtual PPAs used to underpin project financing of large renewable projects in Romania. We are now working on some of the first BESS contracted revenue offtake structures in the country.

The principal structures are physical PPAs (on-site and sleeved structures), virtual PPAs and other synthetic offtake arrangements, often combined with balancing, route-to-market and GoO transfer. Hybrid renewable-plus-storage offtake structures, BESS optimisation agreements, tolling, cap-and-floor and revenue-floor arrangements are also in use. Longer-term hedging and structured offtake products are expected to expand further following the launch of CCP.RO.

BESS market status

Emerging. Romanian regulators increasingly view battery storage as a tool for system flexibility, renewable integration and energy security. Dedicated support measures, including a EUR 150 million state aid scheme for standalone BESS, exemptions from certain financial guarantee requirements and the express inclusion of storage within the new grid-capacity allocation framework, have created a favourable regulatory environment for storage investment. The market is beginning to demonstrate bankability, with Romania closing its first standalone non-recourse BESS project financings and developing early revenue structures such as optimisation agreements, tolling arrangements and revenue-floor mechanisms. While pure merchant revenue stacks remain difficult to finance, lenders are placing increasing reliance on contracted downside protection through optimisation, tolling and floor  arrangements, which are emerging as key bankability drivers for standalone storage.

Grid / curtailment

Romania is facing increasing grid constraints as renewable deployment has outpaced network expansion, resulting in connection bottlenecks, stricter grid access requirements and growing curtailment risk. Romania has replaced the traditional “first come, first served” regime with an auction-based capacity allocation mechanism designed to prioritise projects capable of reaching COD and discourage speculative allocation. Negative prices have already emerged and are expected to become more frequent as renewable capacity continues to grow. Record solar output has periodically exceeded demand and grid absorption capacity. Battery storage is increasingly viewed as both a flexibility and revenue-protection tool, enabling projects to shift output away from low- or negative-price periods, reduce curtailment losses and generate additional revenues from balancing and ancillary services.

Regulatory watch points

The new auction-based grid capacity allocation mechanism replaces the former first-come, first-served regime. Stricter permitting requirements impose financial guarantees and use-it-or-lose-it milestones for grid connection rights, which feed directly into milestone and termination provisions in PPAs. 

BESS benefits from dedicated support, including the EUR 150 million standalone BESS state aid scheme and proposed financial guarantee exemptions, which may improve bankability and encourage the development of BESS offtake structures such as optimisation, tolling and floor arrangements. A potential guarantee exemption for hybrid projects is also under consideration, which could support hybrid renewable-plus-storage offtake structures.

Nuclear generation, including output from Cernavodă, may support firm, low-carbon baseload products, although dedicated nuclear PPA structures remain at an early stage.