Clearing the Way: Strathy South Becomes Scotland's First Oversail and Overrun CPO
Please confirm you are human to start the audio.
Background
As the size of turbine blades and other wind farm components continues to increase, so does the need for developers to secure sufficient land rights for these components to pass over third-party land adjoining the public road, either through the airspace above or by running over the land itself. The rights required to do so are commonly referred to as “oversail” and “overrun” rights. Securing these rights is a significant undertaking for any developer, both in terms of cost and time, as it typically involves negotiating individual voluntary agreements with each affected landowner along the turbine delivery route. Complications can arise, particularly where landowners are unknown or negotiations stall, leaving developers without the certainty they need to meet project timescales. A compulsory purchase order (“CPO”) provides an alternative mechanism: a statutory process through which a developer can acquire the necessary land rights.
The Strathy South Wind Farm is a consented onshore wind development in Sutherland, promoted by SSE Generation Limited (“SSE”), with a generating capacity of up to 196 MW. Construction of the Wind Farm requires the transport of large, indivisible turbine components, with blades of up to 79.5 metres in length, from Scrabster Harbour to the project site, approximately 50 km to the west.
On 26 June 2026, the Scottish Ministers confirmed the Strathy South Wind Farm Compulsory Purchase Order 2023 (the “Order”), which is the first Scottish CPO promoted solely to secure oversail and overrun rights over third party land. Voluntary agreements will remain the preferred route, but this decision may lead to the greater use of CPO as a tool for securing land rights for renewables projects.
Land Rights
SSE promoted the Order in parallel with seeking voluntary agreements with affected landowners, an approach consistent with current planning guidance, which acknowledges the potential benefits of progressing a compulsory purchase order alongside negotiations. This dual-track strategy yielded results as each voluntary agreement that was concluded led to the removal of those plots from the CPO.
Several objectors contended that the Order was unnecessary because heads of terms had been agreed in relation to their land. The Reporter rejected this, concluding that until voluntary agreements were formally completed, there was no certainty that the turbine components could reach the site and the Order therefore remained necessary.
CPO
Although the Reporter stated that he was not convinced the Order would set an important precedent, the Scottish Ministers’ confirmation of the Order has significant implications for developers, landowners, and their advisers in future cases involving the delivery of large-scale renewables components. Though a CPO remains the fallback if voluntary agreements cannot be achieved, it can be used to significantly de-risk the project timeline. However, developers should be mindful of the significant timescales associated with the CPO process itself and potential legal challenges in respect of any decision.
In the decision, the Reporter assessed whether the public benefit outweighed private interests, which is the overriding test under Planning Circular 6/2011. The Reporter noted that Scottish Ministers had already accepted the Strathy South Wind Farm’s significant public benefits when granting section 36 consent. Government policy had also been strengthened since the original consent through NPF4 and the revised Onshore Wind Policy Statement, reinforcing the imperative to deliver large-scale renewables. Against this, the Reporter found that the impact on private interests was limited: the plots comprised small peripheral areas of land adjacent to roads, no buildings or existing businesses were adversely affected, and the acquiring authority offered to reconvey the land after exercising the necessary rights.
This CPO demonstrates that, where a compelling public interest is established and the acquiring authority has acted proportionately, Scottish Ministers may be willing to confirm orders that secure the access rights critical to delivering renewables projects.
Conclusion
The Strathy South decision offers several key takeaways for energy infrastructure developers.
First, the Scottish Ministers have confirmed that CPO powers under the Electricity Act 1989 are available to generation licence holders (including private sector companies) for the purpose of acquiring land to facilitate the transportation of turbine components to a consented wind farm site. This includes the acquisition of oversail and overrun rights over land adjacent to public roads at identified pinch points.
Second, running a CPO in parallel with voluntary negotiations is expressly supported by Scottish Government guidance and was a key consideration in this case. Developers can consider initiating the CPO process, even where voluntary agreements are being actively pursued, to protect delivery timelines – keeping in mind the timescale and legal challenge risks of a CPO decision.
Third, the decision highlights the importance of thorough preparatory work, which may include route option appraisals and other assessments to underpin the case that the Order is necessary and proportionate.
For more information, please contact one of your usual CMS contacts or a member of our Real Estate and Planning Energy and Infrastructure team.
This article was authored by Katrina Reid-McConnell and Anna Andráskó