"If a party is prevented from or delayed in fulfilling its contractual liabilities due to the effects of the COVID-19 pandemic, there may be grounds for invoking force majeure either based on the contract in question or the Finnish law. The threshold for invoking a force majeure event in commercial contracts is high and always subjec to a case-by-case assessment.
The Finnish law in general recognises force majeure as a general principle for limiting a party’s liability even without an express contract provision. As a rule, invoking a force majeure event requires that the event could not be foreseen at the time of entering into the contract and the event prevents or delays the performing party from fulfilling its contractual duty. The affected party should notify the other party of the force majeure event without delay. As a consequence of a force majeure event, the affected party may be relieved from its obligation to perform for the duration of the force majeure event. The Finnish Sale of Goods Act (355/1987) recognises also situations in which a performing party may be relieved from its obligation to perform due to an impediment that the party cannot overcome, and may be relieved from its obligation to pay damages if the damage was caused by an impediment beyond its control. A party’s contractual obligation may also be adjusted or entirely set aside, if the application of the contractual provision in question would lead to an unfair result pursuant to the Finnish Contracts Act (228/1929).
If the contract in question includes a force majeure clause, such clause may limit the potential force majeure events to only those listed in the clause, and these provisions cannot generally be interpreted expansively. A contract may also set out a specific procedure for invoking a force majeure event, such as a notice period and form requirements for the notice. Further, the contract may also specify the consequences of the force majeure event, such as the price and time.
So-called Finnish General Conditions for Building Contracts (‘YSE 1998’) are widely used in the construction contracts in Finland. The YSE 1998 terms include a list of potential force majeure events. The list does not comprise e.g. disease, epidemic or pandemic, but includes e.g. exceptional cirumstances referred to in the Finnish Emergency Powers Act (1552/2011) that may affect the contractor’s possibility to engage necessary workforce or procure materials and equipment as well as other similar unforeseeable and exceptional events beyond the control of the party. Under the YSE 1998 terms, as a rule, a force majeure event may entitle the contractor to a reasonable extension of time. Further, the client may be liable to compensate certain costs to the contractor, such as the site security expenses, heating and other energy costs and the costs of protecting, servicing and maintaining the site. The client is also liable to contribute towards the other costs incurred by the contractor, the size of the contribution amounting to 2 % of the average daily cost of the building contract per working day for the first 5 working days of the interruption and 1 % per working day thereafter. The average daily cost is calculated by dividing the contract price (excl. VAT) by the number of working days in the building contract period."
Social Media cookies collect information about you sharing information from our website via social media tools, or analytics to understand your browsing between social media tools or our Social Media campaigns and our own websites. We do this to optimise the mix of channels to provide you with our content. Details concerning the tools in use are in our privacy policy.