English law cases, although not binding on Scottish courts may be considered. However the leading case in Scotland mentioned above, City Inn Ltd v Shepherd Construction Ltd, differs from the English law position. City Inn found that one must firstly consider whether there was a “dominant” cause of delay i.e.
If a dominant cause can be identified as the cause of some particular delay in the completion of the works, effect will be given to that by leaving out of account any cause or causes which are not material.
Depending on whether or not the dominant cause of delay is one for which the employer is responsible or not, a contractor’s claim for an extension of time to complete the works will or will not succeed.
If however where there are two causes of delay, one being an event for which the employer is responsible and the other being an event for which the contractor is responsible and neither could be described as the dominant cause of delay, the court found that one should then turn to the concept of “apportionment” i.e.
… it is open to the decision maker to apportion the subsequent delay in the completion of the works as between both events and a claim for an extension of time by the contractor would not necessarily fail. In such a situation, which could, as a matter of language, be described as one of concurrent causes, in a broad sense … it will be open to the decision-maker, whether the architect, or other tribunal, approaching the issue in a fair and reasonable way, to apportion the delay in the completion of the works occasioned thereby as between the [event for which the employer is responsible] and the other event.
In how the exercise of apportionment is carried out, the lower court in City Inn Ltd v Shepherd Construction Ltd [2007] CSOH 190, said that the degree of culpability involved in each of the causes of the delay and the “causative significance” of each (including the length of the delay caused and the significance of each) were important. When it comes to approaching that apportionment in a “fair and reasonable way”, the Appeal Court in City Inn also noted that the background, in particular the possibility of a claim for liquidated damages (i.e. fixed damages which may be applied when a contractor does not complete the works by the completion date), must be borne in mind.
It is worth noting that the City Inn decision was specific to standard form wording (the 1980 JCT standard form building contract) which expressly refers to the granting of a “fair and reasonable” extension of time, however it is considered as a leading case on concurrent delay in Scotland and has been the subject of much commentary.
The English courts have subsequently considered and specifically rejected this application of apportionment (as per Adyard Abu Dhabi v SD Marine Services [2011] EWHC 848 (Comm) and Walter Lilly & Company Limited v Giles Patrick Cyril Mackay, DMW Developments Limited [2012] EWHC 1773 (TCC))
Social Media cookies collect information about you sharing information from our website via social media tools, or analytics to understand your browsing between social media tools or our Social Media campaigns and our own websites. We do this to optimise the mix of channels to provide you with our content. Details concerning the tools in use are in our privacy policy.