Under the general rule, the contractor is not responsible for the delay, if it has been caused by the delay of the employer, and vice versa.
Under the law, there is no automatic extension of construction works completion term (the “Extension”). However, there is no statutory restriction for the parties to include provisions on the Extension into the construction contract (either automatic or subject to an additional consent). In case the construction contract does not regulate the issue of the Extension, the Extension will require amendments to the construction contract.
Under the law, a party is entitled to request the Extension subject to amendments to the construction contract in the following cases: (a) a force majeure event; (b) a breach of contractual terms by the employer (e.g. delays in transferring an advance payment, delayed provision of construction materials, equipment); (c) changes to the design specifications and estimates; (d) third parties actions affecting the performance of works, which are not under control of the contractor; (e) other circumstances, which may influence the works completion terms.
If the parties cannot reach agreement as to the Extension in the above cases, the dispute may be referred to the court. The court will carefully analyse whether there are justified and legitimate grounds for the Extension, and whether the requested Extension is proportional to claimed grounds. Should the contract between parties provide for specific procedure for requesting of the Extension, the court will analyse whether such procedure was followed by the requesting party. The cases on such issues rarely come before the courts in Ukraine, as parties usually negotiate such issues and agree acceptable solutions.
If a delay is due to the contractor’s fault, the contractor will be required to pay a penalty or a fine, as provided for in a contract or established by law, and compensate employer’s damages in full. If a delay has been caused by the employer (failure to provide a construction site, non-performance of the obligation to transfer the design specifications and estimates, etc.), the contractor will not be accountable for the delay or suspension of the construction works and may claim compensation of damages caused by the breach of the employer’s obligations.
There is no specific case law relating to concurrent delay in Ukraine. However, in case of a dispute regarding the concurrent delay, courts may take into consideration the following factors: the nature of each event; interconnection of events; gravity of a contractor’s/employer’s breach; whether each party took sufficient efforts to mitigate the situation
Social Media cookies collect information about you sharing information from our website via social media tools, or analytics to understand your browsing between social media tools or our Social Media campaigns and our own websites. We do this to optimise the mix of channels to provide you with our content. Details concerning the tools in use are in our privacy policy.