If concurrent delay is found to exist between events which would have otherwise entitled each party to claim against the other, the so called “no harm, no foul” rule applies and neither party may benefit monetarily from the delay. The contractor may not claim for the costs of delay and receives an extension of time so that the employer does not recover delay damages.
Questions may arise as to whether one of the parties has intentionally delayed in response to the other party’s delay – termed “pacing”. Generally speaking, pacing is legitimate and will not result in a finding of concurrent delay, a principle often voiced by the phrase: “Why hurry up to wait?” However, parties taking such action run the risk that the delay being responded to reduces or resolves in the future, or that subsequent delay analysis shows the supposed pacing to be the original cause of delay.
Earlier cases had found that any concurrent delay would deprive the parties of a financial remedy for delay altogether. These cases pre-date critical path analysis and the popularity of liquidated damages clauses and have now been overtaken by what is referred to as the “apportionment rule” whereby the court will attempt to segregate delays were possible. This is not to be confused with the apportionment of liability for concurrent delay based on relative fault as applied in some other jurisdictions (such as Scotland). Apportionment in the United States refers simply to the process of allocating responsibility for different parts of an overall project delay to individual parties based on a critical path analysis. Where such an analysis shows specific delays to be concurrent, the “no harm, no foul” rule noted above applies and neither party may claim financially in respect of those delays.
The treatment of offsetting delay has recently given rise to controversy as a result of the 2017 ASCE SDAS noted above. This document suggests that delay which is not on the longest path to completion may nonetheless be treated in the same way as concurrent delay if it would independently cause any activity to be delayed beyond the contractual completion date as adjusted. Ultimately the position depends on whether criticality is defined by reference to the contractual completion date or by reference to the longest path to completion. There are cases supporting either approach: see for example Framlau Corp, 71-2 BCA (CCH) and In re Fire Security Systems, Inc, 02-2 BCA (CCH) in favour of offsetting delay being treated in the same way as concurrent delay and Electronic & Missile Facilities, Inc, GSBCA No. 2787, 71-1 BCA for the opposite conclusion. However, the more commonly accepted position (supported by the AACE RP-FSA) is against treating offsetting delay in the same way as concurrent delay and to adopt the longest path to completion as the basis for measuring criticality.
Social Media cookies collect information about you sharing information from our website via social media tools, or analytics to understand your browsing between social media tools or our Social Media campaigns and our own websites. We do this to optimise the mix of channels to provide you with our content. Details concerning the tools in use are in our privacy policy.